HomeTech NewsData Centres & EnergyOptical Fibre Prices Jump Severalfold as AI Demand Outruns Supply Until 2028

Optical Fibre Prices Jump Severalfold as AI Demand Outruns Supply Until 2028

In brief

  • TrendForce (19 October 2026) says AI data centres and high-capacity backbones are driving a global optical-fibre supply shortfall of 180 million fibre-kilometres in 2026.
  • For operators and hyperscalers buying cable now, it projects finished-fibre spot prices at 2.8–5 times 2025 levels or higher, with the squeeze lasting until at least 2028.
  • What’s still unknown: how fast preform expansions (TrendForce: typically 18–24 months) and long-term agreements will rebalance the market.

Every number below is TrendForce’s research estimate or forecast, not a TSN measurement.

What shortage does TrendForce describe?

TrendForce links rising demand from AI data centres, data-centre interconnects and high-capacity backbone builds to a 180 million fibre-kilometre global shortfall in 2026.

It says shortages have tightened since late 2025 and are “expected to persist until at least 2028.”

How far have prices moved, on TrendForce’s figures?

Finished fibre type (TrendForce)Spot / average vs 2025 level (2026)
Finished optical fibre products (overall band)2.8–5 times or higher
Bend-insensitive fibre (in-data-centre cabling)average more than five times
AI backbone fibre (DCI / high-capacity backbone)about 2.8 times
Mainstream telecom fibreabout 3.7 times
Source: TrendForce

How tight is supply?

Indicator (TrendForce)Figure
Global capacity utilisation (2026)92%
Inventoryfrom four months in 2024 to one month
Some leading suppliersbooked into Q1 2027
Preform expansion lead timetypically 18–24 months
Source: TrendForce

How large is demand?

TrendForce estimates global demand at 577 million fibre-kilometres in 2026, with data-centre construction about 18–20% of that total, rising to 30–35% in 2027.

Beyond hyperscale CSPs, it says chipmakers and telecom operators are also investing in related infrastructure, lifting fibre needs for interconnects and backbones.

Are buyers locking supply early?

TrendForce says operators are shifting from short-term purchasing to long-term supply agreements (LTAs). As an example it cites a September 2026 Verizon–Corning multi-year deal for 129 million fibre-kilometres (about 80 million fibre-miles) of high-density fibre and connectivity for delivery 2027–2032, to support broadband and AI data-centre backbones.

That deal is TrendForce’s cited example; TSN is not adding other contract details.

Our read

If TrendForce’s frame holds, fibre — not only GPUs — is a multi-year AI constraint: utilisation near full, inventories thin, and preform capacity slow to add. The practical response it describes is LTAs; the catch for late buyers is paying severalfold spot multiples into 2026 while waiting for 2027–28 supply.

What’s still unknown?

  • How much of the 180 million fibre-km gap closes via LTAs versus new preform lines
  • Regional price dispersion beyond TrendForce’s global averages
  • Whether 2028 is an end date or only a floor for the shortage

How we sourced this

Sources

Related stories

Follow @tsnmediahub on X for breaking AI news as it happens.

Follow on X

Share this story

Latest stories

More in this category

Latest stories

Explore the TSN Atlas: Every topic we cover, mapped. Click a bubble to dive in.