Google has signed a 20-year power purchase agreement (PPA) with Constellation Energy to pay for upgrades that will add 890 MW of new nuclear capacity at 11 operating reactors in Illinois, Pennsylvania and New Jersey. The companies announced the deal on 6 October 2026, saying the extra output will reach the PJM grid before the end of 2032, with the first uprate expected by 2028. [1][2]

Building a new reactor takes the best part of a decade. Squeezing more megawatts out of reactors that already run is usually faster, and this deal is a large bet on that approach. Constellation says it represents more than $4.3 billion of new investment by the company. [2]

What Google Is Committing To

Google says the uprates will add 890 MW of firm, 24/7 clean capacity to PJM, which it describes as roughly the output of a large new reactor delivered years sooner than a greenfield build. PJM runs the grid across 13 Mid-Atlantic and Midwestern states and serves about 67 million people. [1]

Google presents itself as the anchor customer giving Constellation the long-term revenue certainty to invest in 11 of its reactors at six sites, while “ensuring other grid customers bear none of the associated costs”. With this PPA, Google says the nuclear capacity it has enabled in the US from uprates and restarts now exceeds 1.5 GW. [1]

The 890 MW is only part of the commercial package. Constellation’s release says the companies also signed a separate 15-year energy supply agreement for a further 2,700 MW from Constellation’s existing PJM fleet, which it describes as giving its operating plants revenue certainty “without taking resources off of the grid”. Together the two deals cover 3,590 MW, the headline figure CNBC reported, but only the 890 MW is new capacity. The agreement also includes load-shaping and demand-response commitments, so that non-critical consumption can be cut during high-stress grid events. [2][3]

How a Nuclear Uprate Adds Power

An uprate modernises turbines, steam generators and digital control systems so that an existing reactor produces more electricity. Google argues that with 94 US reactors operating and electricity demand rising, the “fastest new megawatt” often comes from existing infrastructure. Nuclear already supplies nearly 20% of US electricity. [1]

Constellation has not formally named the 11 units. A company spokesman told the American Nuclear Society’s Nuclear Newswire that the plants include Braidwood, Byron, LaSalle and Quad Cities in Illinois, Limerick in Pennsylvania and PSEG Nuclear’s Salem in New Jersey, in which Constellation holds a 43% stake. [4]

Jobs and Gemini Enterprise

The companies say the programme will sustain roughly 4,400 existing jobs and create about 7,200 construction jobs during the building period. Under an expanded five-year technology alliance, Constellation will use Google Cloud and Gemini Enterprise agentic workflows to speed up uprate planning and regulatory work, streamline construction, optimise plant output and protect critical infrastructure. [1][2]

Where the Deal Sits in the US Nuclear Push

The US Department of Energy has set a goal of enabling 5 GW of domestic nuclear expansion by 2030 through uprates and restarts, and Constellation says the deal advances the federal UPRISE programme. Google says its agreements to revitalise existing nuclear plants are expected to enable nearly 25% of that national goal by the end of the decade. [1][2]

Three weeks after the Google announcement, on 27 October, the Department of Energy offered Constellation a conditional loan of up to $5 billion for uprates at eight of its plants in Illinois, Maryland and Pennsylvania, which the department says would add nearly 1.1 GW. The commitment is conditional, and Constellation says it is not a final decision to proceed with any individual uprate. The department has been busy on the supply side more broadly: a day later it closed a $5.1bn loan to Alliant Energy for gas plants and storage in Iowa and Wisconsin.

Google’s post also lists other nuclear partnerships: uprates with Georgia Power at four units, where Google cites about $900 million in expected ratepayer benefits; a collaboration with NextEra to restart Iowa’s Duane Arnold Energy Center, at more than 600 MW; and work with Kairos Power and the Tennessee Valley Authority on advanced reactors at Oak Ridge. [1]

Paying for Extra Nuclear Output Is the Least Disruptive Way to Feed Data Centres

Data-centre growth is adding to demand on PJM, and the grid is already tight. In mid-October the Energy Department issued an emergency order letting PJM call on data-centre backup generators during a period of high demand and planned outages. Against that backdrop, a buyer funding new output at existing nuclear plants is a better answer than one that simply contracts existing power away from other customers or leans on diesel generators. Uprates use sites, grid connections and workforces that are already in place, and they add carbon-free power rather than redistributing it.

The deal is less sweeping than the 3,590 MW figure suggests. More than three-quarters of that total is a supply contract for power Constellation’s plants already generate. The new capacity also arrives gradually: one uprate by 2028 and the full 890 MW by the end of 2032, subject to engineering, construction and US Nuclear Regulatory Commission approval. The claim that other ratepayers bear none of the cost is Google’s; it will only be testable once contract terms and the regulatory filings for each unit are public. The use of AI to shorten engineering and licensing work is a sensible application of the technology, provided safety reviews are not shortened along with it.

What Is Still Unknown

  • Commercial terms. Prices and Google’s share of the output versus wider system benefits are not disclosed.
  • Company-reported figures. The 890 MW, 1.5 GW, job counts and the share of the national goal are company figures and have not been independently verified.
  • Delivery risk. Each uprate still needs engineering work, regulatory approval and construction finished on schedule before the end of 2032.

Update, 29 October 2026: An earlier version of this article said a 3,590 MW figure reported elsewhere did not appear in Google’s announcement. Constellation’s own release confirms it: the total combines the 890 MW uprate PPA with a separate 15-year, 2,700 MW supply agreement. The article now reflects both, adds Constellation’s release as a source and names the plants reported to be involved.

Related on TSN: US Offers Constellation a Conditional Loan of Up to $5bn for Uprates

Sources

  1. Google, The Keyword, Amanda Peterson Corio, “Why we’re backing America’s existing nuclear plants”, 6 October 2026
  2. Constellation Energy, “Google and Constellation Announce Landmark Agreement to Bring 890 MW of New Nuclear Capacity to PJM Grid as Part of Long-Term Power Deal”, 6 October 2026
  3. CNBC, “Google enters massive 3.6-GW power deal with Constellation Energy”, 6 October 2026
  4. American Nuclear Society, Nuclear Newswire, “Google, Constellation reach 11-unit uprate plan; Constellation to invest $4.3 billion”, 6 October 2026

Follow @tsnmediahub on X for breaking AI news as it happens.

Follow on X

Share this story

Latest stories

More in this category

Latest stories

Explore the TSN Atlas: Every topic we cover, mapped. Click a bubble to dive in.