HomeTech NewsData Centres & Energykt cloud to Be Sole Tenant of Keppel’s 60MW Ansan Data Centre

kt cloud to Be Sole Tenant of Keppel’s 60MW Ansan Data Centre

kt cloud has committed to take every megawatt of a 60MW greenfield Ansan data centre that Keppel Data Centre Fund III is developing in South Korea. Keppel’s release, dated 26 November 2026, says the fund “has secured kt cloud as the master tenant” and that the Korean operator is “committing to take up 100% of the data centre’s capacity.”

The building does not exist yet. Keppel says construction of the “AI-ready” facility is expected to start in November 2026, and that the site is “targeted to be ready for service by 2030.” It also says the necessary construction permits and power approvals are already in hand. No lease value, rent or capital cost has been disclosed, and Keppel says the agreement is “not expected to have any material impact” on its net tangible assets or earnings per share.

The planned hall is substantial even so. Keppel describes a Tier III-equivalent building with two basement levels and eight floors above ground, a total floor area of about 52,622 square metres, liquid-cooling infrastructure, and 60MW of secured gross power. The Ansan plot itself was acquired by the fund in June 2026 and is its third investment. As of 30 September 2026, Keppel Data Centre Fund III had about S$5.1 billion in funds under management. Keppel says it had 39 data centres with more than 800MW of gross power capacity at the end of 2025.

The operator’s own Korean-language release, also dated 26 November, calls the project Ansan 2 AIDC. It puts the site about 2.5 km from Ansan 1, a 50MW AI data centre the company is already building, and says the two will form a 110MW campus. It also says every floor of the new building will be liquid-cooling ready, and it places the project inside KT Group’s plan to supply more than 1GW of AI data-centre capacity by 2031, a plan that also names Gunsan and Cheongna. The 110MW campus total and the 1GW-plus group target are the tenant’s and KT Group’s figures, not Keppel’s. The release says kt cloud is taking part as a partner in Keppel’s first data-centre development in Korea.

Bong-gyun Kim, chief executive of kt cloud, said “the competitiveness of an AI data centre goes beyond capacity.” For Keppel, a pre-let greenfield site in Greater Seoul is a way to enter Korea with the demand already contracted. For kt cloud, it is a second Ansan building, a few kilometres from the first, rather than a one-off hall.

The local market is tight, on the figures Keppel cites. It points to CBRE Research, dated July 2026, for Greater Seoul absorption of 99.7% in 2024 and 99.4% in 2025. Those occupancy rates are CBRE’s, as cited by Keppel; they describe the market the project is entering, not the utilisation of a hall that has yet to be built.

The same caution belongs on the rest of South Korea’s AI data-centre pipeline, which TSN has been covering as a sequence of permits, power memorandums and campus plans rather than as finished capacity. Seoul has been cutting permit and parking rules for AI data centres, a policy shift aimed at getting projects through faster. Power, not land, is often the tighter constraint: SK Telecom and Hyosung have signed a memorandum on power for AI data centres, and Hyundai has committed affiliates to a Saemangeum AI data-centre build. The Ansan tenancy sits in that same queue. It is a contracted building, not a switch already thrown.

kt cloud has reserved the hall; the campus is still a target

A 100% master tenancy is a strong commercial fact, and it is the one Keppel has put on the record. It is not a statement that 60MW of AI compute will be running in Ansan in 2026, or even that the second building is already in the ground. Construction is expected to start in November 2026, on Keppel’s wording, and the ready-for-service date is a 2030 target. Four years is a long interval in a market where power approvals, equipment lead times and tenant fit-out can all move.

The design language needs a similar pause. “AI-ready” and liquid cooling describe how the building is being planned, including, on the tenant’s account, liquid-cooling provision on every floor. They are not a count of deployed GPUs, and neither company has published a cluster size. The 110MW campus figure simply adds Ansan 2’s 60MW to the 50MW Ansan 1 hall the company is already building nearby. The 1GW-plus ambition by 2031 is a KT Group strategy that also names other sites. Both are useful as statements of intent. Neither is capacity in service.

What is fixed today is narrower. kt cloud has agreed to take all of a 60MW Ansan building owned by Keppel Data Centre Fund III, on a site with permits and power already approved, with a 2030 service target. The open questions are the ones the releases leave blank: the value of the lease, the capital cost, and how much of that 60MW is later filled with actual machines.

Related stories

Sources

Follow @tsnmediahub on X for breaking AI news as it happens.

Follow on X

Share this story

Latest stories

More in this category

Latest stories

Explore the TSN Atlas: Every topic we cover, mapped. Click a bubble to dive in.