About A$3 billion of NextDC’s market value disappeared on Wednesday, 21 October, after the Australian data centre operator said it could no longer count on revenue from its M3 Melbourne campus this year. The shares closed down 41.7%, the company’s worst day since it listed in 2010, Reuters reported. CNBC had them down 39.5% earlier in the session.
The trigger was a stalled power upgrade. Jemena, the electricity distributor that supplies M3 in West Footscray, has suspended part of the network work the campus needs for its next increase in grid supply, and has told NextDC it does not expect to restart before February 2027.
Update, 1 November 2026: this article now includes NextDC’s 26 October board and pay changes and Jemena’s own statement on the paused works.
About A$140 million of M3 revenue is out of the forecast
According to NextDC’s statement to the ASX, net revenue for the year to June 2027 is now expected at A$475 million to A$500 million, down from A$615 million to A$640 million. Underlying EBITDA guidance falls to A$245 million to A$265 million, from A$385 million to A$410 million. Both ranges now exclude the affected customer contracts at M3, which the August guidance had included at about A$140 million each of revenue and EBITDA. Reuters puts that at about US$98 million.
Even capacity already billing is excluded, because while Jemena’s work is suspended the existing supply cannot be relied on for the full contracted power ramp. NextDC says it cannot yet estimate what the contracts will contribute. The contracts allow service level credits when capacity is late or not fully powered, which could push EBITDA below the new range, and in some circumstances give the customer the right to terminate. NextDC is considering whether force majeure or other relief applies.
“We have taken the affected M3 contracts out of FY27 guidance until we can reliably estimate their contribution,” said chief executive Craig Scroggie. “With M3 revenue deferred, we have paused projects not backed by customer contracts and put that capital behind the capacity our customers have already contracted.”
NextDC cuts spending and freezes new sites
Capital expenditure guidance drops to A$4.5 billion to A$5.0 billion, from A$5.25 billion to A$5.75 billion. All new development projects and land acquisitions are on hold “for the foreseeable future”, and the board will look at selling development sites it does not need in the near term. NextDC will report on a full spending review at its annual meeting on 20 November. It had A$8,675 million of liquidity at 30 September, including A$1,275 million in cash, says it complies with its debt covenants, and has no scheduled debt maturity before December 2029.
Five days later, on 26 October, NextDC said in a second ASX release that its board “recognises and shares investors’ disappointment” over the M3 delay. It withdrew a proposed increase in the cap on non-executive directors’ fees, cut incumbent directors’ fees by 10% with immediate effect, and said Scroggie had agreed to forgo his FY27 short- and long-term incentive opportunities. Chairman Douglas Flynn will retire once a successor is in place, and the board expects to appoint a new chair and another independent director in the first quarter of 2027. Shareholders vote at the annual meeting on 20 November.
Residents’ opposition stopped the poles going up
Construction of the data halls continues; the 66kV line feeding them does not. Jemena halted parts of the work in September, citing safety concerns and lack of access to work sites arising from community and stakeholder opposition, NextDC says, and the local council, as road authority, has withheld consent while consultation continues.
Jemena’s own works notice says it has “temporarily paused” the transmission pole upgrades across Yarraville, Footscray and West Footscray “while we take time to listen and better understand the feedback received”. It adds that separate rebuild work at the Footscray West zone substation, which began in 2023 to replace ageing equipment, is unrelated to the paused upgrade.
The ABC reported that the site sits about 15 metres from homes and has long drawn complaints over diesel and noise, and that residents in nearby Yarraville blocked crews installing 15-metre power poles in September. Simon Cooper, NextDC’s chief development officer, told investors the company was looking at other routes, including burying cables. “Undergrounding does take time and there’s not an immediate option that we can work on now,” he said.
The delays stack up. The next grid increase is now expected in the 2028 financial year, and later increases depend on new transformers at the Brooklyn Terminal Station, the first of which NextDC now expects later than planned. A planning permit for further expansion, lodged under Victoria’s Development Facilitation Program, is not now expected until 2027, because the state government enters caretaker mode on 3 November before the 28 November election. “Together with later grid supply, this delays M3’s final capacity stages by several years,” Macquarie analysts said, according to Reuters. Citi warned in a note cited by CNBC that the effect could run beyond FY27, and Treasurer Jim Chalmers said the government was working on national standards for data centre investment.
Local consent is now part of the power supply chain
NextDC built the halls and signed the customer. What it did not control was a distributor’s ability to put poles in a residential street. Reuters reported that RBC’s Tom Beadle called the delays “evidence that community concerns around data centre developments present a real risk to the timing of delivery of contracted capacity”. The same pattern is showing up elsewhere: Memphis has voted for a 135-day pause on new applications, and Amazon has dropped its Ashburn plan after a local supervisor vowed to fight it. Australia has more large projects in the pipeline, including IREN’s proposed 900MW Redbank campus, and each will need its own grid upgrade. For developers, the timetable for the last few kilometres of cable can now matter as much as the one for the building.
Contracted capacity is not the same as delivered capacity
Data centre operators are often valued on signed contracts. NextDC’s release shows how those contracts can unwind when power is late: credits, possible termination rights and a force majeure argument that is still being assessed. The scale of the share fall, against an A$140 million revenue deferral, suggests investors were pricing those wider risks, along with the spending freeze, rather than one year’s numbers. It came less than two weeks after Firmus withdrew its planned ASX listing.
The next marker is 20 November, when NextDC reports its spending review and, possibly, whether its M3 customer is prepared to wait.
Sources
- NextDC, “M3 Melbourne Power Delay and Revised FY27 Guidance”, ASX release (21 October 2026, PDF)
- NextDC, “Board Renewal and AGM Voting Items”, ASX release (26 October 2026, PDF)
- Jemena, “Update on Planned Works in Yarraville and Footscray” (works notice, October 2026)
- Reuters via StreetInsider, “Australian AI data centre operator NextDC shares shed 42% on revenue delay, future plans on hold”, Scott Murdoch and Rajasik Mukherjee (21 October 2026)
- CNBC, “Australian data center operator NextDC’s shares plunge 40% after it slashes earnings forecast” (21 October 2026)
- ABC News, “NextDC value on ASX smashed by delays to West Footscray data centre”, Leanne Wong (21 October 2026)
Get TSN’s biggest tech stories, explained.
News and insights across AI, tech, crypto and cybersecurity. Every source linked. Unsubscribe anytime.
Get the newsletterRelated stories
- IREN Proposes Redbank, a 900MW Data-Centre Campus Near Wagga Wagga
- Microsoft Reportedly Pulls Out of Nscale’s Loughton AI Data Centre in Essex
- Firmus Pulls Its IPO, Isomorphic Labs Eyes $40bn-Plus and StepFun’s Step 5 Goes Live
Follow @tsnmediahub on X for breaking AI news as it happens.
Follow on X