Blackstone Digital Infrastructure Trust has signed a definitive agreement to buy about 75% of 13 Amazon Web Services data-centre buildings, in a sale-and-leaseback valued at about $5 billion.

In a 16 November 2026 press release, Blackstone Digital Infrastructure Trust Inc. (NYSE: BXDC) said it “has signed a definitive agreement to acquire a 75% majority interest in two joint ventures with Amazon Web Services (‘AWS’), in a transaction valued at approximately $5 billion reflecting an initial capitalization rate of 7.0%.” The joint ventures, it said, will own “13 newly constructed powered shells across two AWS data center campuses, with AWS retaining a 25% interest.” AWS “will lease back 100% of the portfolio on a triple net basis with an initial lease term of 12 years and a fully extended lease term of 32 years.” The transaction is BXDC’s “inaugural investment.”

The more precise stakes are in BXDC’s Form 8-K, filed the same day, which describes a Contribution Agreement dated 11 November 2026. Under that filing, BXDC is to acquire a 75.1% controlling interest in each of two joint ventures that will own the campuses, “with an aggregate gross value of $5.0 billion, reflecting an initial capitalization rate of 7.0%.” The AWS side is to retain a 24.9% non-controlling interest. At closing, the company expects to contribute $1.9 billion of cash proceeds from its initial public offering. The AWS retained interest is put at $0.6 billion. The remainder, including transaction costs, is expected to be funded with the net proceeds of about $2.5 billion of new non-recourse mortgage loans secured by the properties.

The 8-K says the 13 newly constructed data centres have “647 megawatts of aggregate information technology power capacity,” with one campus of nine buildings in northern Indiana, described as the greater Chicago data-centre market, and one campus of four buildings in Mississippi. Each campus is to be 100% leased to an Amazon Data Services affiliate on long-term, triple-net leases, with the tenant’s payment obligations guaranteed by Amazon.com, Inc. The 8-K describes the lease terms as a weighted average initial term of 12 years and a weighted average fully extended term of 32 years.

The buildings in this deal are powered shells: the data-centre structures and their power capacity, not the servers or chips that tenants install. BXDC’s release uses that wording; the 8-K describes the same assets as newly constructed data centres. Nothing in either document transfers AWS’s computing equipment.

The transaction “is expected to close in the fourth quarter of 2026 and is subject to certain closing conditions,” the release says. The 8-K is blunter. The transactions, including the loans, “are subject to certain other conditions and may not be completed on their contemplated terms, or at all.” The Contribution Agreement may be terminated by either side if closing has not occurred by 31 December 2026, or a later date extended under the agreement. Nick Pell, chief executive and president of BXDC, called the assets “an attractive match for the deployment of our IPO proceeds.” Prasad Kalyanaraman, vice-president of AWS Infrastructure, said: “Partnering with Blackstone allows us to continue expanding responsibly while keeping communities at the center of how we build.” There is no separate Amazon-side statement beyond that quote in BXDC’s release.

The deal sits in the same capital-and-capacity story as Amazon’s latest quarterly results, in which AWS sales rose 39%, Amazon’s plan to invest more than €16 billion in Germany in 2027, and Blackstone’s larger energy-transition fund. It is a different kind of transaction from Amazon’s decision to drop a data-centre plan in Ashburn, which was about a site that will not be built.

A signed agreement is not a completed purchase of computing kit

A $5 billion headline is easy to misread as Blackstone buying a slice of AWS’s chip fleet. That is not what either document describes. The assets are 13 newly built shells with 647 megawatts of IT power capacity, leased back in full to AWS on a triple-net basis. The tenant, not the landlord, is the party that fills those halls with servers. Treating the megawatt figure as a statement about GPU supply, or as a change in who operates AWS, goes beyond the filing.

The stakes and the timing are also easy to round in the wrong direction. The release’s 75% and 25% are the rounded figures; the 8-K’s 75.1% and 24.9% are the contractual ones. Closing is expected in the fourth quarter of 2026, but it is still subject to conditions, including financing commitments and a minimum cash distribution to the AWS side, and the 8-K expressly says the transactions may not complete on the contemplated terms, or at all. An outside date of 31 December 2026 is a deadline in the agreement, not a promise that the deal will be done by then.

The $1.9 billion of IPO cash that BXDC expects to contribute, and the $2.5 billion of mortgage loans that are expected to fund the rest, describe how the trust proposes to pay for a controlling interest in buildings. They are not a valuation of AWS, and they are not evidence that the campuses are already generating the contracted rent. Until closing, the useful facts are the ones in the release and the 8-K: a signed sale-and-leaseback of powered shells, a 7.0% initial capitalisation rate, a 12-year initial term with a 32-year fully extended term, and a deal that has not yet closed.

Sources

Related stories

Amazon Posts a Record 13.9% Operating Margin as AWS Sales Rise 39% is the closest recent TSN account of AWS’s scale as a capital-hungry cloud business, and is the next read.

Follow @tsnmediahub on X for breaking AI news as it happens.