Enerflex Wins Over 1 GW Gas Power Order for North American Data Centre

Enerflex, the Calgary-based energy equipment company, said on 13 October 2026 that it has been hired to design, engineer, build and assemble more than one gigawatt of gas-fired power generation units for “a large-scale North American data center development”. In its announcement, Enerflex did not name the client or the site, give the contract’s value, or say what kind of engines or turbines the units will use.

The award lifts Enerflex’s backlog of on-site gas power work for data centres past 1.75 gigawatts, with deliveries running through 2028.

What “behind-the-meter” power means

Most buildings get their electricity from the grid, through a meter run by the local utility. A “behind-the-meter” plant sits on the customer’s side of that meter: it makes power on site, for that site, rather than buying it from the grid. Data centre builders are turning to this because grid connections in many places can take years, while AI facilities need large amounts of power now. The question of who pays for that power, and how much gas it burns, is becoming a policy fight, as TSN set out in Who Pays for AI’s Power?

Enerflex describes the units as “low emission”. That is the company’s wording; it gave no emissions figures.

Two awards in two weeks build a 1.75 GW backlog

The 13 October award followed a smaller one. On 1 October, Enerflex said it had been contracted to supply about 450 megawatts of behind-the-meter gas-fired units for a North American data centre developer, with deliveries starting in 2027 and finishing in 2028. Enerflex said the new award, together with others including that 450 MW project, takes its behind-the-meter backlog to more than 1.75 gigawatts. All of the work will be done in its North American factories.

Enerflex’s third-quarter results, published on 29 October, show what that means for the business. Bookings in its Engineered Systems unit, which builds the equipment, reached a record $1.0 billion in the quarter, including the 450 MW award, against $339 million a year earlier. Engineered Systems backlog hit a record $2.1 billion at 30 September. The 1 GW-plus award came after the quarter ended, so it is not in those figures. Group revenue fell to $623 million from $777 million a year earlier, which Enerflex put down to revenue recognised on a large Eastern Hemisphere project and project milestones in the prior-year period.

Enerflex is spending more to build the units

To handle the work, Enerflex has authorised about $100 million of investment in its Engineered Systems facilities. With its Q3 results, it raised the part it expects to spend in 2026 to $30 million to $40 million, from about $15 million, with about $85 million expected in 2027.

Paul Mahoney, Enerflex’s president and chief executive, said: “The demand for reliable, prime power that does not require grid connection, supporting artificial intelligence and digital infrastructure development, continues to grow.” He added that the company hopes to turn more of its pipeline into new projects and follow-on maintenance and digital services. On 1 October Enerflex said that pipeline “continues to exceed 2 GW”.

Gas fills the grid gap, but the bill is still unclear

A single order of more than 1 GW is roughly the output of a large power station, and it is going to one data centre development. That shows how far AI builders are willing to go to avoid waiting for the grid. It also shows who is winning: not just turbine makers, but companies like Enerflex that can package engines, controls and assembly into modular units and ship them quickly. Others are chasing the same gap with different technology, from Mainspring’s linear generators for AEP to the “generator-to-chip” approach from Wärtsilä and Schneider Electric.

What is missing matters as much as what was announced. Without the client, location, price or equipment type, it is impossible to judge the deal’s value or its emissions. “Low emission” gas units still burn fossil fuel, and a plant this size running around the clock would be a significant new source of carbon, even if it is cleaner than older generators. The risk for the AI industry is that power built quickly to meet demand becomes a long-term commitment to gas. The opportunity, if developers follow through, is that on-site plants are later paired with cleaner supply or grid connections once they arrive.

The award also covers equipment only. Enerflex describes commissioning, installation and after-market services as further opportunities, not part of this contract. The next signals to watch are whether the client is named, and whether the 1 GW order shows up in Enerflex’s fourth-quarter bookings.

Update, 30 October 2026: This article has been updated with figures from Enerflex’s third-quarter results, published on 29 October, including its raised 2026 spending on Engineered Systems facilities. It originally said $15 million of the investment was in the 2026 plan.

Sources

Related stories

Follow @tsnmediahub on X for breaking AI news as it happens.

Follow on X

Share this story

Latest stories

More in this category

Latest stories

Explore the TSN Atlas: Every topic we cover, mapped. Click a bubble to dive in.