Western Australia will go without both of its direct internet cables to Singapore until well into November, and the second repair has slipped again. Australia’s research and education network AARNet said in a 22 October update on its status page that work on the Indigo West cable would start on 25 October and finish by early November, while repair of the Australia-Singapore Cable (ASC) would start on 3 November and finish by mid-November. In late September the ASC’s owner, Vocus, had been aiming to complete that repair by 4 November.

AARNet said the new timelines “extend beyond” the late-October estimate it had given earlier, and that restoration depends on vessel availability, weather, permits and the complexity of the work. A repair ship is now on its way. The provider Aus Internet’s status page said at 05:22 UTC on 26 October that the vessel “has now been mobilised and began transit to the repair site”, with an estimated time of repair of 3 November for Indigo West.

How Perth lost both direct routes

The two faults began a month apart. Aus Internet’s incident log says Indigo West went down on 8 August with a shunt fault, a failure in the cable’s power feed, about 47.6 km from the Perth landing station. That fault was repaired on 15 September, but traffic did not return: a second shunt fault on the Singapore side had deteriorated into a full cut.

The ASC broke on 4 September, according to both the internet provider Neptune and the Submarine Cable Status tracker, which lists the cause as not established. Vocus has said the break lies in Indonesian waters, about 615 km from the Singapore landing station.

One ship, two cables and an Indonesian permit

The order of the repairs comes down to what each one switches off. In its update on the Australia-Singapore cable, Vocus said it had agreed to fix Indigo West first, even though the ASC had priority under the repair arrangements, because working on the ASC means powering down the section that now carries services Vocus has restored via Jakarta.

The newest entry on that page, dated 25 September and written by Jonathan Gleeson, Vocus’s general manager of technology operations, set out the original plan: the ship would leave Singapore on 11 October, Indigo West would be fixed around 24 October, and ASC work would start around 25 October with completion targeted for 4 November. Gleeson named Indonesian operational permits and clearances as a key dependency and warned that “these dates may change if operational conditions require”.

They did change. The Submarine Cable Status tracker, citing later Vocus customer updates that TSN could not find on Vocus’s own page, says departure was first pushed back to about 22 October. By 22-23 October the permits were in place and the ship was due to leave Singapore on 23 October. Indigo West is now targeted for about 1 November, and the ASC repair is due to begin around 3 November with completion “currently targeted for approximately 11th November”. The tracker adds that Vocus has planned service interruptions during the ASC work and that unprotected wavelength services will stay down until it is done.

What users are living with meanwhile

Traffic between Perth and Singapore has been taking the long way round. Neptune’s Murry Mukhtarov wrote in an 8 October customer update that a normal round trip takes 45-50 milliseconds, while detours run at 150-400ms. One route through Muscat, Oman, measured about 166ms. The Vocus path through Jakarta comes in at about 53ms, and Neptune offers customers a VPN exit on it. Vocus says it has restored Layer 2 Ethernet services via Jakarta and brought a new 100G path between Japan and Guam into service.

Mukhtarov’s note also forecast the slip. “The Indigo West window has already slipped once, from around 24 October, so we expect the ASC date to move as well,” he wrote. As late as 6 October, Papua New Guinea’s PNG DataCo was still quoting the 24 October and 4 November dates as “the latest confirmed repair programme available”.

Cable failures and the slow business of fixing them are getting political attention elsewhere. The UK has proposed up to 14 years’ jail for subsea cable sabotage, although no cause has been published for either of these faults. New routes are also being planned, such as the Pisces cable linking Ireland with France, Spain and Portugal, and landing stations like the one in IPS’s selected Wakayama proposal are where those routes come ashore.

Two cables only add resilience if they fail separately

Perth’s two direct links to Singapore were supposed to back each other up. For most of September and October, both have been out at once. Indigo West’s trouble started in August, the ASC broke in September, and a Singapore-side fault on the first cable got worse before anyone could reach it. The overlap has left the city relying on detours through Jakarta, Oman and Japan.

The repair plan makes this worse. One vessel is doing both jobs one after the other, and fixing the ASC means turning off the Jakarta stopgap until the work is done. So the backup arrangement itself decides the order of the repairs. For network planners, the useful question is less how many cables a city has and more how many can be fixed at once, by which ship, under whose permits.

Every repair date so far has been a forecast

The ASC finish date has moved from 4 November to about 11 November to “mid-November” as different operators have reported it. The Indigo West date has moved from mid-October to late October to early November. Vocus said from the start that the dates depended on Indonesian approvals and on conditions at sea, and those two factors, not the operators’ wishes, have set the timetable.

For businesses in Western Australia that depend on low latency to South-East Asia, the safest assumption is the latest one published. Even then, AARNet says services will come back progressively, not all at once. The next fixed point is 3 November, when ASC work is due to start. Whether it starts on time will show whether mid-November holds.

Sources

Related stories

Follow @tsnmediahub on X for breaking AI news as it happens.

Follow on X

Share this story

Latest stories

More in this category

Latest stories

Explore the TSN Atlas: Every topic we cover, mapped. Click a bubble to dive in.