LS Electric has signed a 185.3 billion won (about $138.5 million) contract to supply Bloom Energy with high-voltage switchgear and distribution transformers for a fuel-cell-powered data centre in Pennsylvania, the South Korean equipment maker said on 13 October 2026, Yonhap reported.
The order matters less for its size than for what it shows about how AI data centres are now being powered. Rather than wait years for a grid connection, more developers are generating electricity on site, and every on-site plant still needs the conventional electrical gear that switches, protects and steps that power down before it reaches the servers. LS Electric is selling into that gap.
LS Electric’s 38kV switchgear and transformers, delivered from April 2027
LS Electric will deliver 38-kilovolt (kV) high-voltage switchgear and distribution transformers between April and July 2027 for “a fuel cell-based on-site power generation project at a major U.S. technology company’s data center in Pennsylvania”, according to Yonhap. Seoul Economic Daily reported that the data centre is under construction. Neither LS Electric nor Bloom named the customer.
LS Electric said the deal stands out because it supplies the switchgear and the transformers a large data centre needs as a single package. “This contract demonstrates our technical capabilities and ability to execute large-scale projects by supplying switchgear and transformers as a package to a global tech company’s data center,” an LS Electric official told The Korea Herald.
LS Electric’s regulatory filing with Korea’s Financial Supervisory Service, also dated 13 October, adds detail the press reports left out. The formal counterparty is its own US subsidiary, LS ELECTRIC AMERICA Inc., which won the Bloom Energy order; the Korean parent will supply that subsidiary with the switchgear and distribution transformers. The filing puts the contract at USD 138,458,284, converted to 185,257,183,992 won, equal to 3.73% of LS Electric’s 2025 consolidated revenue. It runs from 12 October 2026, the date the purchase order was issued, to 5 July 2027, with no deposit or advance payment: LS Electric will bill as each product is delivered. The filing also notes that the contract period and value may change as the project proceeds.
Switchgear is the set of switches, breakers and fuses that controls and protects electrical circuits. A distribution transformer lowers the voltage so equipment inside a building can use it.
Bloom orders have passed $500m in 18 months
With this contract, LS Electric’s cumulative orders from Bloom Energy have passed $500 million since April 2025, Yonhap and The Korea Herald reported; Seoul Economic Daily put the total at about 668.9 billion won. DCD reported that the previous deal, a 319 billion won ($216.5 million) contract signed in April, was for a large data centre project in New Mexico.
LS Electric serves US customers through local sales, design, production and service centred on LS Electric Utah and its Bastrop campus in Texas, according to Seoul Economic Daily. Local manufacturing matters in a market where transformer lead times have become one of the bottlenecks for new data centres.
The likely site is Aligned’s off-grid Project Phoenix
DCD said that, while not confirmed, the equipment is likely to be for Aligned Data Centers’ Project Phoenix campus in Shippingport, Pennsylvania, where Bloom is expected to deploy up to 2GW of fuel cells. Aligned’s own groundbreaking announcement on 10 September said the three-building, 2GW campus “will use its own dedicated onsite power source rather than the local electrical grid”, next to a former coal plant being redeveloped as a natural gas energy campus. Aligned said the project is expected to send excess power back to the grid once complete.
Bloom’s solid-oxide fuel cells turn natural gas or hydrogen into electricity through a chemical reaction rather than burning it, which Bloom says makes them more efficient and lower in emissions than combustion.
Off-grid power moves the bottleneck rather than removing it
On-site generation is often presented as a way around the grid. This order is a reminder that it swaps one queue for another. A fuel-cell campus still needs switchgear, transformers and protection equipment at a scale close to a utility substation, and those are precisely the items whose delivery times have stretched as AI building has accelerated. A supplier that can promise both pieces together, from US factories, by mid-2027 is offering developers time, which is the scarcest input in the current build-out.
The pattern is now familiar on TSN. AEP plans a $4 billion fuel-cell plant near Cheyenne to sell power to Google, Enerflex won a contract for over 1GW of on-site gas power, and President Trump has said new large data centres are “mandated” to make their own power, although no order has been published. Pennsylvania sits inside PJM, the grid operator that the US Energy Department recently allowed to call on data-centre backup generators in an emergency, so keeping new load off the grid has a clear political appeal there.
The trade-off is that most of this on-site capacity runs on natural gas, so speed comes with emissions that grid-connected renewables might avoid. In Britain the debate is running the other way: a new Data Centre Covenant sets five tests strategic sites must pass for faster grid connections, rather than pushing them off the network. What is missing from this deal is detail: no customer, no megawatt figure and no comment from Bloom. The first hard date is April 2027, when LS Electric’s deliveries are due to begin.
Updated 30 October 2026: added details from LS Electric’s regulatory filing, including the role of its US subsidiary and the payment terms.
Sources
- LS Electric, “Single sales and supply contract” disclosure (in Korean), DART, Financial Supervisory Service, 13 October 2026. https://dart.fss.or.kr/dsaf001/main.do?rcpNo=20261013800054
- Yonhap News Agency (Kim Eun-jung), “LS Electric secures 185.3 bln-won transformer deal in U.S.”, 13 October 2026.
- Seoul Economic Daily (Jang Hyun-ki), “LS ELECTRIC Wins $138 Million Order for U.S. Data Center Power Gear”, 13 October 2026 (AI-translated from Korean).
- The Korea Herald (Lim Ye-jin), “LS Electric lands $138.5m US power equipment deal”, 13 October 2026.
- DCD (Zachary Skidmore), “LS Electric secures $138m order to supply switchgear for Bloom fuel cells at Pennsylvania data center”, 14 October 2026.
- Aligned Data Centers, “Aligned Data Centers and Shippingport Community Mark Revitalization of Legacy Energy Site with Groundbreaking of 2 GW ‘Project Phoenix’ Campus”, 10 September 2026.
Get TSN’s biggest tech stories, explained.
News and insights across AI, tech, crypto and cybersecurity. Every source linked. Unsubscribe anytime.
Get the newsletterRelated stories
- T5 Data Centers Proposes a Fuel-Cell-Powered Data Centre in Chantilly, Virginia: 48 MW of Fuel Cells and Up to 27 MW From the Grid, the Applicant Says
- Wärtsilä, Schneider Electric and Stanley Consultants Launch a “Generator-to-Chip” Approach for US Data-Centre Power; the Speed-Up Is Their Claim
- NTT DATA Picks Bloom Energy for 900 MW of Fuel Cells
Follow @tsnmediahub on X for breaking AI news as it happens.
Follow on X