The New South Wales government has awarded Transgrid the contract to deliver the Hunter Transmission Project, a 110-kilometre, 500 kilovolt line that will form part of the state’s high-voltage backbone. In a 23 November 2026 announcement, EnergyCo said: “The NSW Government has awarded Transgrid the contract to deliver the Hunter Transmission Project.” The same day, Downer EDI told the ASX and NZX that it had been awarded a contract by EnergyCo to work with Transgrid on the line works, “valued at approximately $1.1 billion over a three-year construction period.” The Downer release does not name a currency.
What the Hunter Transmission Project is meant to do
EnergyCo describes the line as “110-kilometre, 500 kilovolt” and says it will carry power from the Central-West Orana and New England renewable energy zones “as ageing coal-fired power stations retire.” The new link will “help create a 500 kilovolt transmission ring,” which the agency says will increase the capacity of the network and help deliver a reliable and affordable electricity system for the state.
That ring language is the strategic point. A single corridor into a region can become a bottleneck as coal plant closes and new wind, solar and storage come online further west and north. Closing a 500 kilovolt loop is intended to give the grid more than one path for that power to reach homes and businesses. It is still a construction programme, not a completed asset.
The project received NSW planning approval in July 2026, “subject to 115 conditions.” EnergyCo says procurement was “overseen by the Australian Energy Regulator.” “Around 90%” of the corridor is on mining, energy and government-owned land, and “Fewer than 20 private properties” are affected, “reduced from 70” in the preliminary corridor. The line is also expected to create 900 jobs during construction. EnergyCo adds that close to 700 local people are already working on construction and specialist trades in the Hunter-Central Coast renewable energy zone — a separate, earlier workforce figure, not a substitute for the 900-job estimate on this project.
Downer’s line works, and when they start
Downer’s scope is “approximately 110 kilometres of new double circuit 500kV transmission line” and lattice steel structures from the Bayswater South to the Olney 500 kilovolt switching stations. Planning, design and procurement are expected to start in December 2026, with on-site mobilisation in 2027 “subject to final approvals.”
That last phrase is doing real work. The delivery contract has been awarded, but the contractor’s own notice still ties the move onto site to approvals that have not all been cleared. Readers should not treat 2027 as a firm start date.
The $1.1 billion figure should be handled the same way. It is Downer’s valuation of its contract “over a three-year construction period,” not an official total cost for the Hunter Transmission Project as a whole, and the announcement does not say whether the amount is in Australian dollars or another currency. EnergyCo’s notice names Transgrid as the delivery contractor and says design-and-construct contractors have also been appointed, but it does not itself state the $1.1 billion figure.
How the official sponsors describe the award
Hannah McCaughey, EnergyCo’s chief executive, said: “Awarding the delivery contract is a major milestone for the Hunter Transmission Project and takes us another important step towards construction.” She called the line a critical piece of infrastructure that would increase network capacity and help unlock new renewable generation and storage, and said EnergyCo would keep working with Transgrid, landowners and communities as the project moves into its next phase.
Brett Redman, Transgrid’s chief executive, said the company and its construction partners were “focused on delivering this essential transmission infrastructure safely and efficiently on behalf of the NSW Government and homes, businesses and industries across the state.” The company, he added, looked forward to working “closely and respectfully with Hunter communities.”
Peter Tompkins, Downer’s chief executive, said: “The award further strengthens Downer’s position in the rapidly growing transmission infrastructure market and supports the Group’s Energy & Utilities growth strategy.” He also said it positioned the company to compete for further work on Australia’s wider transmission investment pipeline, and that Downer looked forward to partnering with EnergyCo and Transgrid, “with a focus on safety, environmental and community outcomes.”
The official narrative, then, is that a long-planned 500 kilovolt link now has a delivery contractor, a line-works partner and a route that has already been narrowed to cut the number of private properties in the corridor. The remaining tests are the ones Downer itself flagged: final approvals, then mobilisation, then three years of construction. Until those approvals are in place, the Hunter Transmission Project is a contracted scheme, not a line under construction.
Sources
Get TSN’s biggest tech stories, explained.
News and insights across AI, tech, crypto and cybersecurity. Every source linked. Unsubscribe anytime.
Get the newsletterRelated stories
- National Grid Asks Ofgem to Approve About £4.5 Billion More Transmission Investment
- DOE Plans Up to $50m DPA Funding for Virginia–West Virginia Transmission